Which Tuscaloosa Riverfront Projects Have Construction Dates, and Which Only Have Approvals?

Crews are driving piles near the Mercedes-Benz Amphitheater for temporary railroad bridge spans. This is one of the first steps in the last phase of the Martin Luther King Jr. Boulevard and Jack Warner Parkway project, City Engineer Mike Gardiner told the Tuscaloosa Thread. The city now expects the work to wrap up in summer 2029.

Leases are being signed and buildings priced along this corridor right now, so that date matters. MLK Boulevard is closed from just north of 6th Street to Jack Warner Parkway near the Nicks Kids Avenue intersection. The trestle parking lot is closed as well, on amphitheater show nights included. Suppose you sign a five-year lease near the riverfront this winter. Close to half of that term falls before the road is finished, and the largest new demand sources nearby don't open until 2028. Underwriting along this stretch of Tuscaloosa starts with the calendar. Each project should be placed by how far along it actually is.

The road is public money buying access

Phase III rebuilds the two spots where rail lines cross the road near the historic wooden trestle. At the larger crossing, which the city calls Warrior Main, the road now squeezes through narrow openings between the trestle's timber supports. City drawings replace those supports with a single span carrying two lanes in each direction, with a shared-use path on one side and a sidewalk on the other. Farther west, the road goes through a narrow gap in an earthen berm under the "Goodrich" spur line. That opening will be widened to two lanes each way, a center turn lane, a path and a sidewalk.

For commercial users, the important line in the plan is about trucks. The Thread reports that the rebuild allows more traffic and larger trucks to reach West Tuscaloosa from downtown. Any delivery-dependent business west of the trestle, from contractors to suppliers to food service, deals with that constraint today. Once the work is done, the corridor from Stillman Boulevard to Almon Avenue will be a four-lane road with a landscaped median, sidewalks, shared-use paths, new lighting and underground utilities.

The funding sits with local agencies. The Tuscaloosa County Road Improvement Commission pays for the full three-phase project, which totals just over $86 million, and the city manages it. Phases 1 and 2 are complete. When ground broke in July, Phase III was estimated at $49 million. The city's presentation at the Chamber of Commerce of West Alabama's Transportation Summit in October put it at $51 million. Scott Bridge Company is the contractor.

Gardiner says the widened road will open a gateway to about 100 acres of unused or underutilized property. The city's July announcement said the work would "unlock more than 100 acres of land in West Tuscaloosa for future development opportunities." At the groundbreaking, State Rep. Chris England said that land could draw a mix of residential, commercial and entertainment development "in the years ahead," and he cited the Saban Center, the amphitheater and nearby hotel development as signs of what is possible.

The 100 acres, then, is a forecast. It is described as a total area and a list of possible uses. A sound underwriting model doesn't treat it as a leasing pipeline yet. The projects England named are the right place to check, because they are the ones that turn the forecast into foot traffic.

Sorting the anchors by stage

The projects people mention in conversations about the riverfront and downtown are at very different stages. Here they are, from most committed to least:

  • Topped out, with a public opening date. The Saban Center is a $120 million arts, science and education campus going up on the former Tuscaloosa News site. Stone Building Company is the general contractor. The project topped out on March 30, 2026, with building completion planned for 2027 and a public opening in spring 2028. The Tuscaloosa News gave the same spring 2028 target on October 20. On October 26 the Center announced a $251,939.59 investment from the Alabama STEM Council for programming, supplies, curriculum and staffing.
  • Ground broken, with a target date. ALUM, a Derek Jeter-backed hospitality company, broke ground in late October on a 116,000-square-foot development near Temerson Square at 22nd Avenue and Fourth Street. The plans include 68 condo-hotel residences, a private members clubhouse, dining and a rooftop lounge. It is expected to employ 70 to 80 people, with opening planned by July 2028, WBRC reported. The Tuscaloosa Thread names Tuscaloosa's Harrison Construction as general contractor.
  • Under construction, ground-floor restaurant. Slim's Pizzeria is planned for a 7,800-square-foot first floor at Greensboro Avenue and 6th Street, with condos above. The partners are Charles Morgan, Miller Mobley and Cris Eddings. Contractor Amason & Associates reported construction underway at the 550 Greensboro Avenue high-rise in January 2026.
  • Approved three times. The Element hotel, a 101-room, six-story project from the Westin portfolio, is proposed near Jack Warner Parkway and Almon Avenue, across from Jim 'N Nick's Bar-B-Q. The City Council first approved it in 2020. Construction didn't start within the allotted time after the 2020 or the September 2022 approval, so it went back to the council each time. The third approval, in February 2025, gave developers 12 months to begin construction or lose the approval, The Crimson White reported. Counting from the February 2025 vote, the latest window ran to about February 2026.
  • Forecast. The 100-plus acres west of the trestle, with uses described as possibilities.

The projects with dates are concentrated downtown and on the east side of the corridor. The one hotel proposed right on Jack Warner Parkway near Almon Avenue has been approved three times since 2020. The land west of the trestle is waiting on a road that isn't scheduled to finish until summer 2029.

Lining the dates up against a lease term

Put the dated items on one timeline:

  1. June 2026: Phase III work begins, with MLK Boulevard and trestle-lot closures following.
  2. 2027: Saban Center building completion.
  3. Spring 2028: Saban Center public opening.
  4. July 2028: ALUM's planned opening.
  5. Summer 2029: Phase III completion, the current city estimate. When the city announced the phase in May, it had estimated about two and a half years of construction.

Mayor Walt Maddox described what ALUM is supposed to add downtown to WBRC:

"It adds hundreds of people who will be in our downtown who will go to our restaurants, go to our shops."

That is the demand case in his own words, and it is scheduled for mid-2028. A tenant who opens in early 2027 pays rent for roughly 18 months before the Saban Center and ALUM open their doors. A user who depends on the trestle route for deliveries waits about two and a half years for the wider road. If the first renewal on a three-year lease comes due in 2030, it comes after all of these projects have delivered. The landlord will know that when the renewal is negotiated.

Owners and tenants carry different sides of the same mismatch:

  • Tenants pay today's rent for access that is limited today. That makes sense when the space works for the business as things stand now. It is risky when the pro forma depends on Saban Center visitors or ALUM members in the first year.
  • Owners who price space on the 2028 story are asking tenants to fund the wait. When a tenant pushes back, it isn't a sign of weak demand. The tenant is pointing out that the demand has a delivery date.
  • Investors looking at land or buildings west of the trestle are betting on the order of events. The road comes first, and private projects follow once the access is real. The Element hotel's history shows that council approval near the corridor doesn't lock in a construction start.

What to do with this before you sign

On this corridor, the usual levers in a lease negotiation tie back to the dates above. Build these into your process:

  • Check the stage of any project a pitch relies on. Topped out, ground broken, under construction and approved are four different levels of certainty. For a hotel or mixed-use project, ask whether construction has started and when the current approval window ends.
  • Match term length to the delivery calendar. A term that ends right before mid-2028 sends your renewal into a landlord's market. A longer initial term with set renewal options keeps more of the upside for the tenant.
  • Talk about access during construction openly. Signage, parking and delivery routes can all change while closures are in place. Updates are posted at tuscaloosaroads.com/mlkjwp, and Tuscaloosa 311 takes questions. Tie concessions such as early free rent or a phased rent schedule to the time when access is limited, not to an arbitrary date.
  • Price owned buildings on what tenants will pay today. Treat the post-2029 access improvement as upside on top, not as the base case.

This is general information about the market and lease structure, not legal or financial advice. Have your attorney and lender review any specific lease or purchase terms.

Our office is on Jack Warner Parkway, so we watch this corridor's schedule as closely as anyone signing space on it. If you're weighing a lease, a renewal or a purchase between downtown and the trestle, Right Space Commercial can tour space with you and go through the construction timeline line by line, then help structure terms that match it. Find your space.